The Contract Labour (Regulation and Abolition) Act is gone. Since 21 November 2025 contract labour sits in Chapter XI of the OSH Code 2020, and the OSH (Central) Rules of 8 May 2026 replaced the CLRA Central Rules of 1971. The idea is the same — a licence for bigger contractors, duties for the principal employer — but the numbers, forms and portals have changed. This is what a thekedar needs to know.
When you need a licence
The contract labour part of the Code applies to every establishment, and every manpower contractor, with 50 or more contract workers on any day in the preceding 12 months (s.45). It does not apply to work of an intermittent or casual nature — up to 120 days in a year, or 60 days if seasonal.
- A covered contractor may not supply or engage contract labour without a licence (s.47(1)). The licence states the maximum headcount and the security amount.
- A principal employer that uses an unlicensed contractor who needed a licence is itself in breach (s.54).
- No fee or commission may be charged to workers for the job (s.49).
- Contract labour is prohibited in core activities, except where the work is normally done through contractors, does not need full-time workers for most of the day, or is a sudden time-bound surge (s.57).
Verify: Some states keep a different threshold (for example 20) under their own rules. Private sites usually follow the state’s OSH rules, so check your state.
Validity, fees and security
Apply in Form XXI on the Shram Suvidha portal; the licence is issued in Form XXII. It is valid for 5 years for the headcount written in it. To go above that headcount, apply for an amendment and pay the extra security first (s.48(3); r.96).
| Workers in the licence | Fee (Central) |
|---|---|
| Up to 49 | Nil |
| 50–100 | ₹1,000 |
| 101–300 | ₹2,000 |
| 301–500 | ₹3,000 |
| 501–1,000 | ₹5,000 |
| 1,001–5,000 | ₹10,000 |
| 5,001–10,000 | ₹20,000 |
| 10,001–20,000 | ₹30,000 |
| Above 20,000 | ₹40,000 |
- Security: a bank guarantee of ₹1,000 per contract worker in the licence (fixed slabs of ₹10–20 crore above 1 lakh workers).
- Renewal: apply 90 to 30 days before expiry, same fee, plus 25% if late. Deemed renewed if not decided in 7 days (r.91).
- Single / all-India licence: one licence for several states or all India from the Central authority, decided within 45 days or auto-generated.
- Work-specific licence: a contractor who does not meet the full criteria can get a licence tied to one work order (s.47(2)).
Verify: These are the Central fees and forms. State rules may have their own fee schedule and form numbers.
Report every work order within 15 days
The licence is only the start. Each work order must be reported on Shram Suvidha within 15 days: principal employer, site, start date, headcount and duration (s.50; r.94). Changes in headcount or conditions are reported too (r.93(5)), and all contract labour must be enrolled in EPF and ESI where those apply (r.93(4)).
- An establishment with 10 or more workers registers once in Form I on Shram Suvidha; the certificate comes in Form III within 7 days or is deemed granted. Already-registered establishments update Form I by about 8-Nov-2026.
- Commencement or cessation of contract-labour or construction work: Form VI within 30 days (r.4).
- Wages: at least the Code on Wages minimum or the agreed rate if higher — a licence condition. Pay by bank or electronic transfer before the 7th day after the wage period, and display the wage period and pay day at the site with a copy to the principal employer (r.98).
Registers and returns to keep
One set of registers now does the work of the old CLRA registers. The Code on Wages registers are deemed to satisfy the OSH ones (r.72(3)). Keep them 5 years, electronically or on paper, in English or Hindi plus the local language, at the site or within 3 km.
| Item | Form | When |
|---|---|---|
| Employee register | XIII (OSH) / I (Code on Wages) | Ongoing |
| Attendance-cum-muster roll | XIV / IX | Daily |
| Wages, OT, advances, fines, deductions | XV / IV | Each wage period |
| Leave with wages | XX | Ongoing |
| Accidents and dangerous occurrences | XIX | Each event |
| Contractor half-yearly return | XVIII | Within 30 days after June and December (30 July, 30 January) |
| Annual return | XVII | By the last day of February |
Every worker also gets an appointment letter before joining (r.6 format), a wage slip (Form XVI, or Form V under the Code on Wages) on or before pay day, and an experience certificate (Form XXIII) on demand.
Verify: Rule 72(5) mentions Form XVIII with the annual upload, while rule 98(7) makes it half-yearly. File both until this is clarified.
The principal employer’s side
If you do not pay wages within 7 days of the wage period, the principal employer must pay within 15 days and recover it from your bills or your security (s.55(3); r.98(8)). The authority can order payment from your security deposit, which you must top up within 15 days or face suspension of the licence.
- It can recover PF and ESI it paid for your workers from you.
- It provides drinking water, toilets, washing and first aid where your workers are on its premises; a canteen at 100+ workers (counting contract labour), a crèche above 50, an ambulance room above 500.
- It is liable for injuries to contract workers on premises it controls, and can claim it back from you.
- Your workers doing the same or similar work as its own workers get the same holidays, hours and conditions of service (r.93(2)), and regular workers an annual increment of at least 2% (r.185).
Verify: The old CLRA rule said “same wage rate” in so many words. The new rule says “conditions of service”; whether that covers equal wages is not settled.
How ThekaFlow does this
ThekaFlow counts workers present per site per month from attendance. If a site reaches 50 workers and there is no current labour licence in Compliance documents, it shows on the Law compliance page. Enter the licence’s Max workers, and ThekaFlow compares it with the workers present in the last 3 months.
- Compliance documents holds the licence, work orders and policies with issue and expiry dates; alerts go out 30 days and 7 days before expiry and on the day.
- Contractor returns builds the site-wise figures for Form XVIII (half-yearly) and Form XVII (annual) as Excel, and records when each was filed.
- Registers Form I, IV, IX, XIII and XX per site and month; appointment letters and ID cards from the worker master.
Full steps with screenshots: https://thekaflow.com/guide/compliance/
Questions
Does a contractor with 30 workers need a labour licence?
Under the Central rules, no. The licence is needed when there were 50 or more contract workers on any day in the preceding 12 months. Some states keep a lower threshold under their own rules, so check your state.
How long is a contract labour licence valid?
5 years, for the headcount stated in it. Apply for renewal 90 to 30 days before expiry; a late application costs 25% extra.
What is the licence fee?
Central fees go by headcount: nil up to 49 workers, ₹1,000 for 50–100, ₹2,000 for 101–300, ₹3,000 for 301–500, up to ₹40,000 above 20,000 workers. A bank guarantee of ₹1,000 per worker is also needed.
What must I report after getting a work order?
Within 15 days, report the work order on Shram Suvidha with the principal employer, site, start date, headcount and duration. Changes in headcount must also be reported.
What happens if I pay wages late?
If wages are not paid within 7 days of the wage period, the principal employer must pay within 15 days and recover the amount from your bills or security deposit.
हिंदी में
पुराना CLRA क़ानून 21 नवंबर 2025 से OSH Code 2020 में समा गया है। पिछले 12 महीनों में किसी भी दिन 50 या ज़्यादा ठेका मज़दूर रखने वाले ठेकेदार को लाइसेंस चाहिए, जो 5 साल चलता है। हर वर्क ऑर्डर की सूचना 15 दिन में Shram Suvidha पर देनी है, और रजिस्टर, छमाही Form XVIII और सालाना Form XVII रखने हैं।
This is a plain-language guide, not legal advice. Laws, rates and dates change, and states issue their own rules. Always check the latest central or state notification, or ask your CA or labour consultant, before you act on it.